Further to a number of questions from residents and based on information received from Countryside, the timescale for completion of the Radial Distributor Road (“RDR”), which is planned to run from Essex Regiment Way to the Boreham Interchange, is as follows:
RDR Phase 1 (through Channels)
Completed
RDR Phase 2a and 2b
Construction from May 2019, due for completion June 2020
Boreham Interchange Works
Completed by September 2020 (subject to approval by Highways England)
Generals Lane Bridge Demolition
Completed by January 2021
RDR Phase 3
Construction from May 2021, due for completion September 2021
A pdf version of the above image and key dates can be found here.