Brassie Wood Road Surfacing

Please be advised that Bellway have programmed in remedial works along Brassie Wood in anticipation of the Bus Route change at the end of June. The programme is as follows:-

Current Work
Raising iron works to both areas highlighted on diagram below.

Thursday 13th June
The shaded area in yellow/orange to have 40-60mm of the current surface (binder) planed off and replaced in accordance with Highways Essex instruction. There will be disruption on Brassie Wood from Plots 159 to Plot 169 on this day. Chris (Site Manager) will contact clients individually that live along this part of the road.

Friday 14th June & Monday 17th June
Remedial works to kerbs and preparation for surface/topping layer.

Thursday 20th June
The whole area highlighted will receive the finishing surface coat inclusive of a patch near the temporary bus stop. Again there will be disruption on this day whilst surface works are carried out. Chris will contact the clients individually who are directly affected by this.

Update 19/06/19:
Due to a problem with the facility that manufactures the tarmac, the works will now be completed on Friday 21st June. All affected clients have been contacted by Chris however please be aware that there will be disruption along the entire stretch of road for a further day.