Remedial Work to Kerbs & Raising of Ironworks
Please see below a drawing showing the area where Barconn will imminently be carrying out remedial works to the kerbs and raising ironworks on the roads in readiness for the tarmac topping.
- Kerb works to commence January 22nd along Mashie Link;
- Kerb works to follow from January 23rd/24th January along Fairway Drive (from Newt crossing to raised block paving);
- Raising of ironworks along Mashie Link and Fairway Drive to commence on Thursday 24th January.
The site team envisages that the remedial kerb works will be completed within 2 weeks however the raised ironworks will remain until the road is ‘topped out’, which is booked for early March 2019.